August 26 Update

Published on August 26, 2015 under RRnews
  • The road work on the 100 block of W. Main is scheduled to be complete by the end of next week. There will still be work to be done on the sidewalks after that time.
  • Round Rock Avenue traffic will be rerouted as soon as the W. Main roadwork is completed late next week. Traffic from I-35 will be routed right on Brown St. and left on W. Main in order to access the Mays intersection. The left turn from Round Rock Ave. to W. Liberty Ave. will remain accessible.
  • Crews will continue work on sidewalks, ramps and streetlights on the west side of Mays over the next several weeks.
  • Crews will move to the east side of Mays in late September or early October.

The post August 26 Update appeared first on City of Round Rock.

Source: City of Round Rock